LAKE CO. SANITATION DIST.-GEYERS GEOTHERMAL PIPELINE

Summary

SCH Number
1996102661
Lead Agency
Lake County
Document Title
LAKE CO. SANITATION DIST.-GEYERS GEOTHERMAL PIPELINE
Document Type
NOD - Notice of Determination
Received
Posted
1/19/1996
Document Description
FROM LAKE WATER INTAKE ON EAST SHORE OF CLEAR LAKE TO TREATMENT PLANT NORTH OF CLEARLAKE. PIPELINE EXTENDS SOUTH ALONG HWY 29. THEN WEST, CROSS COUNTRY, ACROSS HARRIS CREEK, BIG CANYON CREEK, AND INTO MIDDLETOWN TREATMENT PLANT-FROM THE TREATMENT PLANT THE PIPELINE CROSSES HWY 175 AND EXTENDS WESTWARD UP INTO THE GEYSERS. ADDENDUM TO EIR FOR REALIGNMENT OF GEYSERS GEOTHERMAL PIPELINE PROJECT WHICH CONSISTS OF A SERIES OF 8 MODIFICATIONS IN THE APPROVED ALIGNMENT OF THE EFFLUENT PIPELINE.

Contact Information

Name
STEVE ZALUSKY
Agency Name
COMMUNITY DEVELOPMENT DEPT-PLANNING DEPT
Contact Types
Lead/Public Agency

Location

Cities
LAKE CO.
Counties
Lake

Notice of Determination

Approving Agency
N/A

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes