Pacific Commons Conceptual Site Plan Approval, c/o Sean Whiskeman, Catellus Development Corporation (PLN2004-00010, PLN2004-00011 and PLN2004-00019)

14 Documents in Project

Summary

SCH Number
1996052016
Lead Agency
City of Fremont
Document Title
Pacific Commons Conceptual Site Plan Approval, c/o Sean Whiskeman, Catellus Development Corporation (PLN2004-00010, PLN2004-00011 and PLN2004-00019)
Document Type
NOD - Notice of Determination
Received
Posted
9/22/2003
Present Land Use
Vacant/General Plan: Industrial, Commercial/Industrial overlay/Open Space, Planned District Zoning.
Document Description
The Conceptual Site Plan Approval pertains to the majority of the land within Pacific Commons that was recently approved for retail development through the Planned District Major Amendment (PLN2003-00166). Specifically, the Concept Site Plans relate to Planning Areas 1, 2 & 3 and would allow for the development of a community retail shopping center and a major retail area, with a total of approximately 710,000 square feet of new retail space. The Conceptual Site Plan Approval is required to identify the overall strategy for the development of an entire Planning Area and the coordination of major site systems such as building orientation, vehicular circulation, parking, pedestrian connections, plaza area locations and conceptual utility plans.

Contact Information

Name
Wayne Morris
Agency Name
Department of Fish and Game /Central Region Coast
Contact Types
Lead/Public Agency

Location

Cities
Fremont
Counties
Alameda
Cross Streets
I-880 and Auto Mall Parkway
Total Acres
768+
Parcel #
Various
State Highways
I-880
Railways
Union Pacific
Waterways
San Francisco Bay

Notice of Determination

Approving Agency
City of Fremont, City Council
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.