California State University San Bernardino, Parking Structures I and II, Schematic Plan Approval

15 Documents in Project

Summary

SCH Number
1996041050
Lead Agency
California State University Board of Trustees
Document Title
California State University San Bernardino, Parking Structures I and II, Schematic Plan Approval
Document Type
NOD - Notice of Determination
Received
Posted
7/14/2006
Document Description
The proposed project is the development of the Northern Access Road with a newly proposed access point to Northpark Boulevard. The Northern Access Road will be constructed within the campus from Little Mountain Road on the eastern boundary of the property, north and westward around the campus core, and joining with the future extension of Pepperlindin and Devil's Canyon Road. The road will be extended on the northeasterly portion of the campus as an extension of the Northern Access Road to provide an additional northerly access to the campus off of Northpark Boulevard. The project is found to be consistent with the Final EIR for the CSUSB Master Plan Revision Certified on February 1997.

Contact Information

Name
B. Michael Wahl
Agency Name
CSU San Bernardino, CPD&C
Contact Types
Lead/Public Agency

Location

Cities
San Bernardino
Counties
San Bernardino
State Highways
I-215
Other Location Info
Intersection of University Parkway and Northpark Boulevard, California State University, San Bernardino.

Notice of Determination

Approving Agency
CSUSB Capital Planning Design and Construction
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print