Reopening of the Central Disposal Site

13 Documents in Project

Summary

SCH Number
1995073068
Lead Agency
Sonoma County
Document Title
Reopening of the Central Disposal Site
Document Type
NOD - Notice of Determination
Received
Posted
4/9/2013
Document Description
The County proposes to construct new waste cells within the currently permitted footprint of the Central Disposal Site, and complete waste disposal operations in accordance with a all applicable regulatory and permit requirements. The following areas are proposed to receive waste as part of this project: the remaining phases of Landfill 2 (Phases III, IV and V), the Compost Area of Land 1, and the Rock Extraction (within the 1971 permitted footprint). No change in operations from those already analyzed in prior environmental documents are proposed, other than incorporating more protective liners in the construction of landfills ceels, and the addition of a "preferential pathway" system in areas where the liner system abuts and overlaps Landfill 1, in order to direct leachate to leachate collection system. These are additional environmental protections above those described in prior environmental documents.

Contact Information

Name
Diana Hennoulie
Agency Name
No. Coast RWQCB
Contact Types
Lead/Public Agency

Location

Cities
Cotati, Petaluma
Counties
Sonoma
Cross Streets
Stony Point Rd. / Mecham Rd.
Total Acres
389
Parcel #
024-080-19,18
State Highways
116,101
Schools
Dunham Elementary
Waterways
Stemple Creek
Township
5N
Range
8w
Section
3,4
Base
MT DIA

Notice of Determination

Approving Agency
No. Coast RWQCB
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print