BAYSIDE COGENERATION FACILITY, NATIONAL CITY

Summary

SCH Number
1994106671
Lead Agency
San Diego, Port of
Document Title
BAYSIDE COGENERATION FACILITY, NATIONAL CITY
Document Type
NOD - Notice of Determination
Received
Posted
2/28/1994
Document Description
CONSTRUCTION AND OPERATION OF ELECTRICAL POWER PLANT AND WATER DESALINATION PLANT

Contact Information

Name
RALPH T. HICKS
Agency Name
PORT OF SAN DIEGO
Contact Types
Lead/Public Agency

Location

Cities
National City
Counties
San Diego
Other Location Info
1400 TIDELANDS AVE

Notice of Determination

Approving Agency
N/A

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print