Geysers Recharge Project Construction Addendum Lano and Mark West Segments

19 Documents in Project

Summary

SCH Number
1994103069
Lead Agency
City of Santa Rosa
Document Title
Geysers Recharge Project Construction Addendum Lano and Mark West Segments
Document Type
NOD - Notice of Determination
Received
Posted
1/27/2000
Present Land Use
Varies. Mostly rural residential and agricultural. Some industrial and business/office.
Document Description
The Santa Rosa Subregional Long-Term Wastewater Project involves certain improvements to the treatment plant, condtruction of a 35 mile long buried transmission pipeline which can supply a constant 11 mgd of reclaimed water from Delta Pond to the Geysers steamfield for recharge via a network of distribution pipes in injection wells. Four-pressure pump stations will lift the water in steps up to the geysers. Some of the remaining flow of the wastewater from the Subregional system will be used to supply the existing discharge system at a rate that will not exceed 5 precent of Russian River flows. The project also includes certain contingency measures to prevent excess discharge.

Contact Information

Name
Marie Meredith
Agency Name
City of Santa Rosa
Contact Types
Lead/Public Agency

Location

Cities
Santa Rosa
Counties
Sonoma
Cross Streets
Numerous
Total Acres
130
Parcel #
Approximately 400, see Appendix F of Supplemental EIR
State Highways
101,12,16
Railways
Nothwestern Pacific
Airports
Sonoma County Airport
Waterways
Russian River, Santa Rosa Creek, Laguna de Santa Rosa
Township
6N,7N
Range
8/9W
Section
variou
Base
Mt diabl

Notice of Determination

Approving Agency
N/A

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.