G3 Enterprises Byron San Mine Expansion Project [California Endangered Species Act (CESA) Incidental Take Permit No. 2081-2015-017-03 (ITP)]

5 Documents in Project

Summary

SCH Number
1991113070
Lead Agency
Contra Costa County
Document Title
G3 Enterprises Byron San Mine Expansion Project [California Endangered Species Act (CESA) Incidental Take Permit No. 2081-2015-017-03 (ITP)]
Document Type
NOD - Notice of Determination
Received
Posted
1/6/2016
Document Description
The G3 Byron Mine Expansion Project encomposses 103.3 acres of grassland habitat that contains 0.18 acres is seasonal pond habitat. The project shall impact 103.3 acres and 0.16 acres of the seasonal pond habitat. The project shall also provide protection, mitigation and enhancement activities on 443.1 acres. The expansion shall occur in two locations within the G3 Byron Sand Mine, 73.3 acres and shall be permanently impacted in the area designated the Coarse Beds and 30 acres in the area designated Evo-East. The expansion shall occur in three phases in the Coarse Beds section of the project. Phase 1A shall occur in Coarse Beds North and shall impact 18.0 acres from 2015 to 2020. Phase 1A Project site shall serve as the new settling pond begging in 2020. Phase 1B shall occur in the Central Coarse Beds and shall impact 9.9 acres from 2015 to 2022. Phase 2 shall occur in the Coarse Beds North and shall impact 12.4 acres from 2018 to 2022; Phase 3 shall occur in Coarse Beds South and shall impact 29.0 acres from 2020 to 2028. Screening and Hopper Equipment shall impact an additional 4 acres in the central course bed area and shall operate from 2015 to 2028. Commencement of Phase 2 shall require the construction and verifications of viable ponds by CDFW in Mitigation Areas 1 and 2. Failure to construct viable pond shall result in a staggered Phase 2 based on the seasonal life cycle of Covered Species. Expansion of mine activities in the Evo-East portion of the project shall permanently impact 30 acres of grassland habitat and shall be initiated simultaneously with Covered Activities in Phase 1 of Coarse Beds North from 2015 to 2028. The Evo-East site shall consist of a mine quarry, screening/hopper equipment and an overburden area for top-soil and ore. The impact includes 20.5 acres for the quarry, 5.5 acres for the rejection and overburden and 4 acres for the screening and hopper equipment.

Contact Information

Name
Robert Stanley
Agency Name
CDFW Bay Delta Region
Contact Types
Lead/Public Agency

Location

Cities
Byron, Martinez
Counties
Contra Costa

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print