Redwood Landfill Solid Waste Facilities Permit

23 Documents in Project

Summary

SCH Number
1991033042
Lead Agency
Marin County
Document Title
Redwood Landfill Solid Waste Facilities Permit
Document Type
NOD - Notice of Determination
Received
Posted
12/24/2008
Present Land Use
BFC-A-60 (Bayfront Conservation Agriculture, 1 unit/60 acres) / Bayfront Conservation Overlay
Document Description
Redwood Landfill, Inc. has applied to the Marin Co. Environmental Health Services Dept. for a Revised Solid Waste Facilities Permit (SWFP) for continuation and capacity expansion of a 222.5 acre landfill on a 420-acre site near Novato, Ca. The approved project involves changes to the existing landfill and composting operations as described in the environmental review documents, the SWFP and technical documents developed in conjunction with the SWFP, including but not limited to: increasing the capacity of the landfill to 26.1 million cubicyards (including cover), increasing the number of vehicles that may enter the site per day, changing the slope configuration of the landfill, clarifying the footprint of the landfill, combining the existing landfill and compost permits, adding food waste as a compost feed stock , modifying tonnage allocations for landfill and compost operations, modifying landfilling practices, modifying environmental controls at the site, increasing receipts of recyclables, changing the configuration of the site and development of landfill gas to energy and solar power generation. Redwood Landfill will continue to be the principal serving Marin Co.

Contact Information

Name
Tim Haddad
Agency Name
Marin County
Contact Types
Lead/Public Agency

Location

Cities
Novato
Counties
Marin
Zip
94949
Parcel #
125-160-13
State Highways
101
Railways
NW Pacific
Airports
Gnoss Field
Schools
Petaluma Academy
Waterways
San Antonio Creek, Petaluma River

Notice of Determination

Approving Agency
Marin County
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.