CONDITIONAL USE PERMIT #3, ZONE MAP #9-25

3 Documents in Project

Summary

SCH Number
1990020575
Lead Agency
Kern County
Document Title
CONDITIONAL USE PERMIT #3, ZONE MAP #9-25
Document Type
NOP - Notice of Preparation of a Draft EIR
Received
Document Description
EXPANSION OF A BIOMASS POWER PLANT CURRENTLY UNDER CONSTRUCTION. THE ENTIRE PLANNED FACILITY WILL CONSIST OF TWO BIOMAS FUELED FLUIDIZED BED BOILERS DRIVING TURBINE GENERATOR. SALES OF THE POWER IS GENERATED TO SOUTHERN CALIFORNIA EDISON. THE POWER PLANT WILL BE FUELED BY AGRICULTURAL AND WOOD FUELS HAULED IN FROM KERN AND ADJACENT COUNTRIES.

Contact Information

Name
FRED SIMON
Agency Name
KERN COUNTY PLANNING DEPT.
Contact Types
Lead/Public Agency

Location

Cities
Delano
Counties
Kern
Cross Streets
POND ROAD AND STATE HIGHWAY 99
Total Acres
124
State Highways
99
Railways
SPRR
Airports
DELANO MUNICIPA
Township
25
Range
25
Section
25
Base
MDB&M

Notice of Completion

State Review Period Start
State Review Period End
Local Actions
Use Permit
Project Issues
Agriculture and Forestry Resources, Air Quality, Flood Plain/Flooding, Noise

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.