Addendum to the FInal EIS/EIR for the Coachella Canal Lining Project;

8 Documents in Project

Summary

SCH Number
1990020408
Lead Agency
Coachella Valley Water District (CVWD)
Document Title
Addendum to the FInal EIS/EIR for the Coachella Canal Lining Project;
Document Type
NOD - Notice of Determination
Received
Posted
9/27/2004
Document Description
California Department of Fish and Game is executing a Lake and Streambed Alteration Agreement number 1600-2004-0074-R6 pursuant to Section 1602 of the Fish and Game Code to the project applicant, Coachella Valley Water District. The proposed project consists of the construction of a new concrete-lined canal parallel and adjacent to the westerly side of the existing canal and continuous from up to 500 feet upstream of Siphon 7 to just downstream of Siphon 32, a distance of approximately 36.5 miles of which approximately 35 miles is new lined canal, and 1.5 miles is replaced siphons.

Contact Information

Name
Kimberly Nicol
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Counties
Imperial, Riverside
Cross Streets
Coachella Canal, Hot Mineral Spa, Frink, and Beal Roads
Total Acres
270
Jobs
492
State Highways
111
Railways
Eagle Mountain, Souther Pacific
Waterways
Coachella Canal, East Highline Canal, and Salt Creek
Other Location Info
Coachella Canal from Siphon 7 to Siphon 32.

Notice of Determination

Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.