Pacific Center East Specific Plan

6 Documents in Project

Summary

SCH Number
1989091320
Lead Agency
City of Tustin
Document Title
Pacific Center East Specific Plan
Document Type
NOD - Notice of Determination
Received
Posted
5/12/2003
Present Land Use
Planned Community Commercial/Business Planned Community-Pacific Center East Specific Plan
Document Description
The project consists of two phases and includes various street improvements: 1) extension and widening of Newport Ave.; 2) widening of, and addition of one travel lane in each direction on Newport Ave.; 3) construction of a new intersection at Edinger Ave. and Newport Ave.; 4) construction of a railroad bridge to allow Newport Ave. to pass under the railroad tracks; 5) rerouting of a flood control channel to a box culvert to allow Newport Ave. to pass over the flood channel; 6) reconfiguration of the Edinger Ave. northbound SR-55 on and off ramps; 7) widening of Valencia Ave. on the north side to four travel lanes; 8) widening of Del Amo Ave. to four lanes and realignment to intersect with Newport Ave.; 9) construction of new Edinger Ave. and Newport Ave. intersection; 10) provision of new and modified signalization at certain intersections; 11) addition of new landscaping, medians and parkways along northbound SR-55 ramps and the southerly Newport Ave. extension; 12) right-of-way acquisition; 13) formation of a utility undergrounding district; 14) possible formation of an assessment district and/or community facilities district. A boundary reorganization is also proposed.

Contact Information

Name
Scott Reekstin
Agency Name
City of Tustin
Contact Types
Lead/Public Agency

Location

Cities
Tustin
Counties
Orange
Cross Streets
Edinger Avenue, Del Amo Avenue
State Highways
SR-55
Railways
SCRAA/OCTA

Notice of Determination

Approving Agency
City of Tustin and Tustin Community Redevelopment Agency
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print