ROUNDHILL SUBSTATION TO STATELINE SUBSTATION TRANS. LINE

2 Documents in Project

Summary

SCH Number
1987042009
Lead Agency
City of South Lake Tahoe
Document Title
ROUNDHILL SUBSTATION TO STATELINE SUBSTATION TRANS. LINE
Document Type
NOD - Notice of Determination
Received
Posted
6/13/1989
Document Description
EXPAND SUBSTATION 250' TO SW AND 90' TO NW

Contact Information

Name
MARY KAY HANNINGER
Agency Name
Contact Types
Lead/Public Agency

Location

Cities
South Lake Tahoe

Notice of Determination

Approving Agency
N/A

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print