Sacramento Solar Highways Project
4 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2011032036
- Lead Agency
- Sacramento Municipal Utility District
- Document Title
- Sacramento Solar Highways Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 7/21/2011
- Present Land Use
- The proposed project would be located within Caltrans-operated right-of-way of Highway 50.
- Document Description
- NOTE: Revised Final 1 Hard Copy The proposed project is a demonstration project intended to determine the feasibility of installing photovoltaic electrical generation on publicity-owned land along the state's highways and freeways. The project would be located in the crescent shaped parcel of land above the northern onramp to westbound Highway 50 at the Mather Field Road Interchange in Rancho Cordova, a short length of cutslope west of that onramp, and the north cutslope between 43rd and 59th streets in the City of Sacramento. The total generation capacity expected is approximately 1.4 megawatts.
- Contact Information
-
Kimberly Crawford
Sacramento Municipal Utility District
Lead/Public Agency
P.O. Box 15830, MS B203
Sacramento, CA 95852-1830
Phone : (916) 732-5063
Location
- Cities
- Rancho Cordova Sacramento
- Counties
- Sacramento
- Cross Streets
- 48th & 59th Streets and Hwy 50 (95817) / Mather Field Road & Hwy 50
- Total Acres
- 4
- State Highways
- Hwy 50
- Railways
- Light Rail/UPRR
- Airports
- Mather Airport
- Schools
- See attached
- Waterways
- American River
Notice of Determination
- Approving Agency
- Sacramento Municipal Utility District
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- Sacramento Municipal Utility District, 6201 S Street, CA 95817-1899.
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.